                                    PROLOK INSTALLATIONJULY 20258. The final panel will need to becut to fit the remaining area. Cutpanel 1%u201d wider(Prolok rib height) than theremaining area and fold up 1%u201d to matchthe Prolok ribs, and provide a bench for the gable trim to sit on.NON-VENTED RIDGE9a. Once panels are completedthe next step is to installclosure strips along the topof the panels. After closuresare complete, install Z Barin the 1.5%u201d space left betweenthe ridge and the panels.VENTED RIDGE9b. Once panels are completedthe next step is to installprofile vent clips, 1 per ft. Fasten the clip on the bottom only to start. Bend up the frontof the clip to slide in the profile vent. Then fasten down the topof the clip. The top of the clip should line up with the top of the panel. 
                                